Shore Road East
New & refurbished beach huts
Completed summer 2020
The Project
As a major gateway for people visiting Poole beaches, the project at Shore Road and here at Shore Road East offered the opportunity to create a greater sense of arrival and welcome to the area.
At Shore Road East 12 beach huts (nos 73-84) have been refurbished and a first floor extension built above, with 6 standard huts, and 2 premier beach huts with L shaped balconies.
Works progress gallery
Final pictures 17th June 2020






×![]()
9th June 2020


×![]()
28th May 2020


×![]()
21st March 2020

×![]()
2nd March 2020


×![]()
13th January 2020



×![]()
16th December




×![]()
21st November




×![]()
25th September-12th November 2019




×![]()
BEFORE WORKS: 12 single storey beach huts at Shore Road East

×![]()
Approved beach hut designs, Shore Road East (Nos. 73-84)
Project timeline
- June 2018 Planning permission granted (Application APP/18/00165/F) for a first floor extension of 6 standard and 2 premier beach huts and the refurbishment of 12 existing ground floor beach huts.
- November 2018 Tender for construction issued
- July 2019 Stepnell Ltd appointed as contractor
- September 2019 Works started on site 2nd September
Also at Shore Road seafront:
- Enhanced public area and seating, refurbished toilets and showers, new beach office and more …
- Further details and progress pictures at the Shore Road project page
Published: 14 March, 2024, Last modified:14 March, 2024
Project Details
- Budget £340,000
- Funding BCP Council
- Project Lead Anthony Rogers, Head of Leisure
- Main Contractor Stepnell Ltd.

Funded by the government’s